|
CO2-Enhanced Coal Bed Methane Recovery |
There are vast, deep coalbeds in Alberta, Canada which are unmineable but contain trapped methane. The Alberta Research Council (ARC) is leading a group of provincial, national and international organizations to exploit the coalbed methane by testing a novel process of injecting carbon dioxide. This process is called Enhanced Gas Recovery (EGR). It is similar to the established practice of using CO2 injection to enhance production from oil reservoirs. With EGR, the injected CO2 is adsorbed in the coal, to be stored in its pore matrix, releasing the trapped methane that can be collected and sold.
Future work in this area could lead to the design of efficient null-greenhouse-gas emission power plants that would be fuelled either by mineable coal or by methane released from the deep unmineable coal. In such a process, the CO2 produced from power plant would be injected into the coalbeds to produce more methane, so continuing the cycle. In addition, a geological sink would be established in the coalbeds, virtually eliminating any release of CO2 to the atmosphere. An abundance of deep coalbeds in Canada and the USA makes geological storage of CO2 applicable to many areas where coal-burning power plants are located.

Schematic of a coal bed methane power plant cycle; a lifecyle approach to
producing fossil fuel
Burlington Resources has successfully injected CO2 into relatively high permeability coalbeds in the San Juan basin in the USA for several years. They are stimulating coalbed methane production and recovery. The injected CO2 is adsorbed into the coal matrix and remains in the ground after completion of gas production. However, further testing and demonstration are needed to apply this process to low permeability reservoirs such as those found in Alberta, Canada and elsewhere in the world.
The ARC-led project has two main objectives:
The overall project is divided into three phases:
I. The proof of concept study - initial assessment and feasibility of injecting CO2, nitrogen, and flue gases into Mannville coals.
II. The design and implementation of a micro-pilot test following Amoco Production Company procedures.
III. The design and implementation of a full-scale pilot project.
The Phase I proof of concept study was completed in July 1997. Based on the success of Phase I, the project passed the first go/no-go decision and proceeded to Phase II, consisting of three tasks: (1) geology, geotechnical and engineering, (2) numerical modelling and (3) a micro-pilot field test. Phase II was successfully completed in April 1999.
ARC’s partners in Phase II included Sproule International Ltd., Canadian Association of Petroleum Producers, IEA Greenhouse Gas R&D Programme, Alberta Department of Energy, Environment Canada, US Department of Energy, UK Department of Trade and Industry, Gulf Canada Resources, Burlington Resources, BP Exploration (Alaska) Inc., Suncor Energy, Canadian Fracmaster, Air Liquide Canada, TransAlta Utilities, EPCOR Utilities, Western Economic Partnership Agreement, PanCanadian Petroleum Limited, Netherlands Institute of Applied Geoscience and Mobil Oil Canada.
The field test was carried out in an existing Gulf Canada well at Fenn Big Valley, Alberta. The test was designed to meet three primary goals: (1) to accurately measure data from a single well test, involving a series of CO2 injection/soak cycles followed by production of CO2 and methane; (2) to match the measured data with a comprehensive coal gas reservoir simulation model to obtain estimates of reservoir properties and sorption behaviour; (3) to use calibrated simulation models to predict the behaviour of a larger scale pilot project or full field development. Phase II is a preliminary and necessary step leading to the planning of a full-scale 5-spot pilot test.
The field test was a success. All three primary goals established for the test have been met: the data set that has been collected is of high quality; accurate estimates of reservoir properties and sorption behaviour have been obtained; and from use of calibrated simulation models, it has been concluded that a full-scale pilot CO2 or flue gas sequestration/EGR project is possible at the Fenn Big Valley location.
From an economic perspective, flue gas injection offers better economics than pure CO2 injection (unless there is a credit for CO2). Since it takes 2 cubic feet of CO2 for each cubic feet of methane produced, the CO2 would account for US $2.00 per thousand cubic feet of methane sold (assuming CO2 at US$1.00 per thousand standard cubic feet, or US$19 per tonne). In addition, considering both economic and CO2 sequestration factors, there might be an advantage to optimising the CO2/N2 composition of the flue gas.
Flue gas injection has merit, as the CO2 will remain sorbed in the coal while the majority of the nitrogen will be produced along with the hydrocarbons. Technical issues that need to be addressed in the next phase of the development are flue gas conditioning, compression and delivery, and N2/CH4 separation. In addition, flue gas injection appears to enhance methane production to a greater degree than is possible with CO2 alone while still sequestering CO2.
In terms of numerical modelling tool, the three software products evaluated so far were adequate for predicting primary production of coalbed methane. However, only one was suitable for modelling flue gas injection. None of the reservoir simulation software products were capable of accurately predicting the produced gas composition observed during the field test. Improved understanding of the process mechanisms, for example, multiple gas sorption and diffusion, and changes in coal matrix volume due to sorption or desorption of CO2, are needed to guide the future development of the simulation models.
Based on the Phase II results, the project has passed the second go/no-go decision and proceeded to Phase III. Phase III is divided into two parts, in stages from 1999 to 2001. Phase III-A begins by evaluating options for the treatment of flue gases, compression, and the associated economics to optimize CO2 storage and methane production both at the pilot and commercial scales. ARC expect to drill and complete a second well and perform a simulated flue gas micro-pilot test. This will be the world’s first pilot test of injecting flue gas into a coal seam.
In October 1999, the second well was successfully drilled and completed at Fenn Big Valley. Core samples were collected to allow accurate determination of the gas-in-place volume, gas composition, and gas storage capacity. A second micro-pilot test will be performed in December 1999, by injecting a simulated flue gas stream consisting of N2 and CO2. The combination of gases may result in greater hydrocarbon recovery without hindrance to the CO2 sequestration. The second micro-pilot will allow us to finalize the design of the full-scale project to be installed in the year 2000 and operated until 2001.

Cutting coal core samples in the field
In parallel, during 1999/2000, geological studies will be carried out to evaluate the geology of other coal deposits in Alberta, such as those in the Ardley and Edmonton groups. The Ardley coals are located at shallower depths and may be more permeable than the Mannville coal allowing lower injection pressures and reduced costs. The Edmonton coals are located at shallow depths in close proximity to major power plants and would be convenient for CO2 sequestration. The reservoir properties in these other areas, in particular the natural fracture permeability, cannot be determined by study of available geologic data. As a result, two formation evaluation wells will be drilled into Ardley and Edmonton coal seams during 2000.
If Phase III-A is successful, the project will proceed to Phase III-B, which is the implementation of an isolated 5-spot pilot with four injection wells and one production well, sized between 20 and 40 acres. The goal of the large-scale pilot is to visibly demonstrate that CO2 sequestration and EGR is possible. A product of the pilot will be complete specifications of the technology required to perform large-scale projects. The specifications will include those for a flue gas collection and treatment module, a compression module, and a gas production module. The methods used to collect and interpret the data and to determine the degree of technical and economic success of the pilot will be fully documented.
The pilot will be performed at the Fenn Big Valley site unless the data from the 1999/2000 formation evaluation tests strongly suggests that the pilot should be located at a shallower, more permeable location. Three additional wells will be drilled in 2000. These are the two remaining injection wells and the production well. The 1998 and 1999 micro-pilot wells will be converted to injection wells. Injection will begin in 2000 and will continue for 12 months into 2001. If the pilot is successful, full-scale development can begin in 2002.
For further information, contact Bill Gunter at Alberta
Research Council, 250 Karl Clark Rd., Edmonton, Alberta, T6N 1E4, Canada.
Tel: +1 780 4505467; Fax: + 1 780 4505083, gunter@arc.ab.ca